Have any questions or concerns?

Project Overview



Bus Rapid Transit or BRT combines the capacity and speed of light rail with the lower cost construction of an integrated bus system. Once complete, Ogden Express (formerly route 603) will provide riders a clean-air ride in an electric bus from the Ogden FrontRunner Station, through downtown, along dedicated bus lanes in the center of the road on Harrison Boulevard and through the Weber State University campus, and to McKay-Dee Hospital. When operational, riders will be able to catch the bus every 10-15 minutes on weekdays and 15-30 minutes on weekends. The project will benefit the community by reducing vehicle trips, supporting the economy and providing transportation choices.

Download Quick Facts

Download Frequently Asked Questions

Transit Improvements



Roadway/Pedestrian/Bike Improvements



23rd Street
Road reconstruction


Washington Blvd
Road reconstruction & pedestrian crossings    


25th Street
Road reconstruction
Harrison Blvd
New widened roads, pedestrian crossings
& adding turn lanes on 32nd & 36th Streets

WSU Campus
New shared use path with road reconstruction
pedestrian crossings and bike lanes

4400 South
Road reconstruction


Construction

Utah Transit Authority, Jacobs Engineering, AECOM, WCEC, and Stacy and Witbeck have partnered to design and construct the Ogden Express (OGX) line over the next three years. Project segments will be constructed simultaneously in multiple locations to ensure project completion in a timely manner.

Updates this Week:

  • Washington Blvd.: Dec. 6-8, crews tentatively plan to install signage between 24th and 25th streets. This will be a rolling operation with minimal traffic impacts expected. UDOT repaving project is wrapping up between 22nd and 40th streets.
  • 25th Street: Potholing operations (underground utility locating) are planned Dec. 6-11 between Adams Ave. and Jefferson Ave., with minimal traffic impacts. Full roadway reconstruction between Washington Blvd. and Jefferson Ave. is expected to begin in early January 2022. City waterline project is wrapping up between Adams Ave. and Van Buren Ave.
  • Harrison Blvd.: Utility relocations continue southward from 32nd St. and a new traffic signal pole installation is planned next week on the southeast corner of the 32nd St. intersection. Utility relocations are underway at 36th St. and retaining wall construction continues at the Family Dollar. Removals are expected to begin next week in the 34th St. area to prepare for retaining wall installation. Traffic is shifted to the east side of the road between 31st and 37th streets and two lanes are maintained in each direction.
  • Weber State University: Retaining wall installation is underway through the Wildcat Village student housing area to 4225 S. Utility work (gas) is planned next week at the Ice Sheet. Utility installations and station platform work continue at Village Drive and the Dee Events Center.

Click Here for More Updates

Construction Timeline




Project Partners




Funding


Get Notified

To stay up to date on the latest and greatest news about construction and the Ogden BRT, we suggest you take advantage of these great resources during this project:


Environmental Assessment

An Environmental Assessment (EA) was completed for the project in 2019. The purpose of the EA was to identify the environmental effects associated with project construction and operation and to provide agencies and the public an opportunity to review and comment on the effects of the proposed project. The EA evaluated impacts to socioeconomic, environmental, and transportation conditions in the project area and what further actions or mitigation could be implemented to address the identified impacts.


Finding of No Significant Impact

 

Environmental Re-Evaluation

Select Language: