Project Description:
The South Jordan Downtown TRAX station project is constructing a new TRAX platform on the Red Line in South Jordan at approximately 11000 South Grandville Avenue, to accommodate population and commercial growth in the area. Construction began Summer of 2024 and is anticipated to be complete Spring of 2025. This project will pour concrete pillars to build the new station and will only affect Sunday travel on 9/22, 9/29, 10/13, 10/20, as well as 10/25-10/27, between Daybreak Parkway Station and 5600 West Station. Riders are advised to begin their trip at either station to avoid delays. Expect 15-to-30-minute delays.
Project Purpose and Benefit:
The project will provide an additional TRAX station for South Jordan service.
Start Date: Sunday, September 22 2024
End Date: Sunday, October 20, 2024
Shutdown: October 25 - 27
Project Schedule:
Pour 1 – West side south – September 22
Pour 2 – West side north – September 29
Pour 3 – East side south – October 13
Pour 4 – East Side north – October 20
Shutdown – October 25-27
Project Map:
Impacted stations: South Jordan Downtown Parkway TRAX station
What to Expect:
- Riders: Bus bridge from 5600 W Old Bingham Hwy Station to Daybreak Parkway Station on Sundays 9/22, 9/29, 10/13, 10/20; and 10/25-10/27; 15-to-30-minute delays.
- Alternative Routes: Begin your trip at either 5600 W Old Bingham Hwy Station or Daybreak Parkway Station to avoid delays.
Residents: 24-hour construction noise from heavy equipment and vehicles
For more information
- Expected Rider Delays: 15-30 minutes
- Regular Service Resumes: Monday after each pour on 9/23, 9/30, 10/14, 10/21, 10/28
- Plan Your Trip: www.rideuta.com/redline
- Service Alerts: www.rideuta.com/signup