Updated 2/4/2008

**Notice: FrontRunner Trains will continue testing daily until the system opens in spring 2008. Be Safe. Always Expect a Train. Never Go Around a Lowered Gate. Don’t Walk, Bike or Play on Railroad Tracks. **


Click Here to enlarge map (pdf, 200 kb)


Construction updates for Area 6:
Updated 2/4/2008.

Cecil to Pleasant View

—Mid February:  Track Construction, Special Trackwork arriving in February and March

Pleasant View Station

—Early February:  Pour PCC Pad  



Construction updates for Area 5:
Updated 2/4/2008.

Ogden Union Pacific Yard and Bridge

—Mid February:  Bridge Guardrails—complete

Ogden Station

—Mid February:  Windscreen Installation



Construction updates for Area 4:
Updated 2/4/2008.

Roy Station

—Early February:  Earthwork Balancing—complete, Park & Ride Curb & Gutter Work, Light Pole Foundations and Conduit



Construction updates for Area 3:
Updated 2/4/2008.

1500 South (Woods Cross) to Old Mill (Kaysville)

—February:  Trackwork Substantially Complete, Ongoing Vehicle Testing

Farmington Station

—Early February:  Concrete Pour for Bridge Elevator at Park & Ride Lot Side, Bridge Brick Work at Station Side

—Mid February:  Elevator Install at Station Side

Old Mill (Kaysville) to 700 South (Clearfield)

—Early February:  Ongoing Vehicles Testing 

Layton Station

—Mid February: Electrical Power Hook-Up, Park & Ride Concrete Finishes

Clearfield Station

—Late February:  Canopy in Fabrication, Park & Ride Concrete Finishes  

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                              

Construction updates for Area 2:
Updated 2/4/2008.

600 North to 1800 North (Salt Lake City)

—Mid February: Track Surfacing, Track Rehabilitation--complete

1800 North (Salt Lake City) to 1500 South (North Salt Lake)

—Mid February:  Clearing Dirt and Other Materials   

Woods Cross Station

—Mid February: Install Sheet Metal Skin on Canopy



Construction updates for Area 1:
Updated 2/4/2008.

200 South to 800 South (Salt Lake City)

—Early February:  De-stress and Welding

Salt Lake Central Station (Intermodal Hub)

—Mid January: Eastern (splitter) Footing and Stem wall--complete, Cap Off Back Fill at Center Platform, Place Snowmelt

200 South to 600 North (Salt Lake City)

—February: Signal and Track Connections—Ongoing