Click here for overview of University Avenue construction.

Construction Information

Construction is scheduled for University Avenue between 700 North and 400 South from Winter 2017 to Spring 2017.

3/17/17 Construction Update

Construction Progress In This Segment

Section 5 Progress Update


Storm drain installation on Univ. Ave. in Provo. 

Median storm drain installation is underway on University Ave. between 400 N. and 600 N. and begins next week between 200 S. and 500 S.

Preliminary signal work continues at Freedom Blvd., various intersections between 700 N. and 1200 S. and at 180 E./E. Bay Blvd. Underground boring is underway between 780 S. and 1200 S.

Traffic Impacts

  • During median storm drain work, traffic is shifted to the outside lanes, on-street parking is restricted, the center turn lane is closed in the work zone and periodic left-turn lane closures are effective at intersections. Thru-traffic lanes remain open on University Ave. and cross-streets during the work. Business and pedestrian accesses are open.
  • Intermittent shoulder and sidewalk closures are in place to facilitate preliminary signal work.