Construction Information

Construction is scheduled to begin in the median of University Parkway between 400 West and 800 East later this summer. This work will clear a path for the BRT portion of the project. Work on the outside lanes is scheduled from Fall 2016 through Summer 2017. Access will be maintained to all businesses. Watch for updates as more information becomes available.

2/17/17 Construction Update

Construction Progress In This Segment


Removals on University Parkway in Orem.

Utility line relocations (telecommunications, water, power, gas) and storm drain installation are underway on the south side of the road between 400 W. and Main Street.

Traffic Impacts:

  • Traffic has been shifted to the roadway center. Drivers are advised to reduce speeds and watch for lane shifts. Left-turns are permitted only at intersections.
  • Business accesses are being maintained. On-street parking has been eliminated.